Project experience

Qadir Engineering (Pvt.) Ltd., Lahore

Complete retrofit and modernisation of 3 × 350 Ton, 3 × 630 Ton, 2 × 800 Ton, 2 × 500 Ton and 2 × 165 Ton machines.

The brief

What the plant needed.

A twelve-machine UBE fleet spanning five tonnage classes, from 165 to 800 Ton, needed modernising without taking the whole floor out of production. Control platforms were ageing and spares for the original electronics were becoming difficult to source.

The plant could not afford a shutdown, so the programme had to be structured around continuous output — every machine returned to service before the next was taken down.

Project detail

Retrofit & Modernisation

2014–2018

Complete retrofit and modernisation of 3 × 350 Ton, 3 × 630 Ton, 2 × 800 Ton, 2 × 500 Ton and 2 × 165 Ton machines.

UBE — Japan

Automotive

How we worked

Our approach on site.

01

Assess

We survey the machine on site, capture the full fault set and agree the scope in writing before any work starts.

02

Rectify

Mechanical, hydraulic and control work is carried out by our own engineers rather than subcontracted.

03

Commission

The machine is run under production load and signed off, with operator orientation delivered at handover.

What we did

Scope of work.

Four workstreams, run machine by machine so the plant kept producing throughout the programme.

12Machines
  1. 01 Control retrofit Complete control retrofit with current-generation drives, replacing electronics that were no longer supportable.
  2. 02 Hydraulic overhaul Hydraulic system overhaul with valve replacement, restoring clean pressure and repeatable movement.
  3. 03 Shot-end rebuild Shot-end rebuild and accumulator servicing, bringing injection performance back into specification.
  4. 04 Phased changeover Machine-by-machine changeover to protect plant output, with each unit back in production before the next came down.
The result

Back in production.

The fleet was modernised machine by machine over four years, each one returned to production before the next was taken down, so the plant never lost more than a single machine at a time.

  • Obsolete control electronics replaced with supportable platforms
  • One machine down at a time across the programme
  • Spares availability restored across the fleet